Your project implementation plan defines 12 capabilities of the planned systems solution that will not be needed once the new solution is operational. What type of requirements are these?

Your project implementation plan defines 12 capabilities of the planned systems solution that will not be needed once the new solution is operational. What type of requirements are these?

A. Functional requirements

B. Nonfunctional requirements

C. Reusable requirements

D. Transition requirements


Answer

D.

Transition requirements describe capabilities that a solution must have to facilitate transitioning from the current to the desired future state. They are not needed once the transition is complete and cannot be created until both the current and new solutions have been defined.